What the training cost is made of
The cost of rollout training is the sum of three items: the training service in the offer, the working hours of the participants and any additional hours beyond the scope. The first is visible in the quote. The second depends on how many people the plant sends and how it values them internally. The third arises when someone adds training after handover.
In one offer, the item for configuring the server and the instance together with training for administrators, technical staff and security accounted for about 19% of the rollout (own calculation from the quote). This shows the scale: training is a significant but not dominant part of the rollout.
Person-hours calculation for three groups
We adopt the scope from one of the rollout offers: 2 administrators for 6 hours each, 6 managers and coordinators for 2 hours each and 12 employees for 1 hour each. Each group gives 12 person-hours, which is a coincidence of numbers, not a rule.
Total: 2 x 6 = 12, 6 x 2 = 12, 12 x 1 = 12, in sum 36 person-hours. For the plant this equals almost four and a half working days of one person working eight hours a day.
- Administrators: 12 person-hours for 2 people.
- Managers and coordinators: 12 person-hours for 6 people.
- Employees: 12 person-hours for 12 people.
- Total: 36 person-hours of the plant's own work.
Training person-hours by group
What it costs in złoty
The plant values its own working hour according to its own rates, so we adopt an example assumption: 80 PLN per person-hour, including employer costs. For 36 person-hours this gives 2,880 PLN. This is a cost that does not appear in the offer and usually lands in the budget of the safety or production department.
For comparison: trainings and work beyond the scope are settled indicatively at about 300 PLN gross per hour plus travel (indicative rates from 2025-2026 rollouts; individual quote). Ten such hours come to about 3,000 PLN gross. That is why it pays to count the training hours in advance and record them in the plan, rather than buy them afterwards.
How to plan person-hours in the budget
First rule: administrator person-hours are planned at the start of the rollout, because configuration depends on them. Second: employees are trained in windows when production has a break anyway, for example at the start of a shift. Third: managers and coordinators are combined into one date, to avoid three separate meetings.
Training in a room takes place on two dates of about 3 hours each, in groups of up to 12 people. It is worth splitting the 12 employees from the example into two dates of 6, instead of taking everyone off the line at once.
What reduces the training cost
The biggest saving comes from good preparation of materials. When the plant delivers the list of companies, training materials, permit templates and the plant layout on time, administrator training does not stretch by hours spent searching for them. The second source of savings is having two administrators from the start: there is no need to organize repeated training after the only administrator leaves.
Training for the rollout when another module is launched falls within the support under the maintenance agreement, so the expansion does not add a separate item for the briefing itself.
Person-hours and own cost of training
| Parameter | Value |
|---|---|
| Administrators | 2 people x 6 hours |
| Managers and coordinators | 6 people x 2 hours |
| Employees | 12 people x 1 hour |
| Cost of own person-hour (assumption) | 80 PLN |
Result: 36 person-hours, about 2,880 PLN of the plant's own labor cost
Note: Sample calculation. The plant enters its own hourly rate; additional hours are settled according to an individual quote.
Video
Frequently asked questions
Should person-hours be included in the rollout budget?
It is worth it, because it is a real cost, although invisible on the invoice. Enter it in the budget of the department the participants come from.
Is the 80 PLN rate an InnerWeb rate?
No. It is an assumed example of the cost of the plant's own working hour. InnerWeb service prices are an individual quote.
How much do additional hours cost?
Indicatively about 300 PLN gross per hour plus travel (indicative rates from 2025-2026 rollouts; individual quote).