What SLA consists of in a maintenance contract
SLA describes three things: service availability per month, response time to a report, and repair time. The SLA parameters (availability, response and repair times) are set in the maintenance contract, for example availability of 99.5% per month, and they depend on the incident type: a strategic failure has stricter limits than a minor fault.
The basis of assessment is the report from the service desk system, which records the moment of reporting, taking up service and closing. This way the parties do not argue about definitions, they read the same time stamps. Purchasing should assess SLA from this angle: what matters is the transparency of measurement and the real repair time, not just the wording in the table.
Availability of 99.5% converted into minutes
It is always worth converting the availability percentage into minutes per calendar month. A 30-day month has 43,200 minutes, so availability of 99.5% means permitted downtime of up to 216 minutes, that is 3.6 hours. Availability of 99% is 432 minutes, and 99.9% is about 43 minutes.
The difference between 99.5% and 99.9% looks small, but for a plant running three shifts it is the difference between a few hours and several dozen minutes of unavailability per month. Purchasing should therefore ask not for the percentage, but for how many minutes are acceptable for a given process.
- 99% in a 30-day month: 432 minutes,
- 99.5%: 216 minutes,
- 99.9%: about 43 minutes.
Permitted downtime in a 30-day month
How to read the report from the service desk system
The report has three time stamps: reporting, taking up service and closing. Response time is counted from reporting to taking up service, and repair time from taking up service to closing. The limits for individual incident types are written in the maintenance contract.
Example for illustration: if the response limit is 12 hours and the actual response took 13 hours, the report will show one hour over the limit. Purchasing can ask for a sample report before signing the contract, so that no definitions are disputed later.
Cost of an hour of own production downtime
For the plant budget the cost of production downtime matters more than the contract clauses. Assume, for illustration, that an hour of system unavailability stops permit issuing on the floor, and an hour of stoppage costs PLN 1,200 according to controlling. Availability of 99.5% allows 3.6 hours of downtime per month, which in this example gives an exposure of up to PLN 4,320 per month.
This calculation is illustrative and does not describe any specific plant. The value of an hour of downtime is taken from controlling, and the number of hours from the accepted availability level. It is also worth calculating a 99.9% variant, to judge whether the more expensive service level pays off.
SLA and business continuity of the plant
SLA is part of continuity planning, not insurance against downtime. Continuity is supported by backups, a twin pre-production instance and emergency procedures on the plant side, for example a printout of current permits for the time of a failure.
When comparing two offers, one compares not only the availability percentage, but also reporting channels, service hours, and the scope covered by backups, updates and security patches.
Conclusions for purchasing
First, record the SLA parameters and the report template in the maintenance contract. Second, name a person on the plant side who checks the reports every month. Third, convert availability into minutes and compare it with the cost of an hour of own production downtime. These three steps turn the SLA clause into a tool that can be used, while the price of the service remains individual.
Availability in minutes and cost of downtime
| Parameter | Value |
|---|---|
| Calendar month | 43,200 minutes (30 days) |
| Availability | 99.5 % |
| Cost of an hour of own production downtime | 1,200 PLN (illustrative assumption) |
Result: Availability of 99.5% allows up to 216 minutes, that is 3.6 hours of downtime per month; at PLN 1,200 per hour the exposure is up to PLN 4,320 per month.
Note: Illustrative calculation on the assumptions above; it does not concern a specific contract or plant.
Video
Frequently asked questions
How many minutes of downtime does 99.5% allow per month?
In a 30-day month up to 216 minutes, that is 3.6 hours. This is an illustrative calculation.
Where are SLA parameters recorded?
In the maintenance contract: availability, response and repair times are set for individual incident types.
Where do response and repair times come from?
From the report in the service desk system, which records the reporting, taking up service and closing.
Does SLA replace a business continuity plan?
No. SLA describes the service, while continuity is supported by backups, pre-production and emergency procedures.
Is implementation included in the SLA cost?
No. Implementation is a separate item in the valuation, and maintenance and SLA are described in the maintenance contract.