The situation: a plant that cannot stop
An insulation materials manufacturer runs continuously: furnaces and production lines operate without breaks, and service crews work inside a running organism. During the analysis period the plant admitted about 20 contractor companies and issued 106 permits in 9 weeks. Two halls, the warehouse and the production hall, accounted for 76 of those 106 permits.
Data from the plant's instance showed a clear rhythm. As many as 82% of permits were issued between 6:00 and 10:00, and 62 of 106 fell on Tuesday and Wednesday. None were issued at weekends. The four largest companies held 63% of permits. This means the gatehouse receives traffic concentrated in a few hours and a few days, not spread evenly.
The problem: security has nothing to check a contractor with
Security had no tool to answer one question: does this person have training, qualifications for the permitted work, a permit for today and an active account. The list of people on site and the evacuation list were compiled by hand, so at the busiest moment of the day they were the least reliable.
The second problem concerned permit locations. As many as 44 of 106 permits pointed to a general location, such as a building or a whole line, instead of a specific machine. Security therefore could not see work on the right line, and the plant did not know where service crews were really returning.
Which work dominates
In the analysed period 43 permits were issued for hot work and 40 for work at height. In the warehouse hall, work at height accounted for 24 of 39 permits, and in the production hall hot work for 24 of 37. These are the jobs where a mistake about qualifications or training costs the most, so entry conditions are checked for them first.
Distribution of 106 permits by day of the week
The solution: a QR scan and four conditions
Security scans the QR code from a badge or a phone. The first scan records entry, the second records exit. The system checks four conditions: training, qualifications for the permitted work, a permit for today and an active account. A missing condition means no entry, and the reason appears on the screen. The guard does not interpret a full permit view but reads the verdict.
- A list of people on site split into guests, couriers, suppliers, plant employees and external companies.
- An evacuation list built from the same scans, printable with one click.
- A group of uncertain persons for those who did not scan out, flagged within a 24-hour window.
- Health and safety training before entry on the contractor's phone: a video or PDF and a test of random questions, with the pass mark set in the panel.
- Invitation by e-mail or SMS, with the company coordinator seeing only their own company.
- A weekly report on missing training sent to designated people.
Limits of the solution
The system does not control a gate or a barrier, does not recognise faces and does not use NFC. The guard lets people in physically, while the system provides a verdict and a record. The control makes sense only after the contractor register is imported and badges are assigned, so this stage must be planned before the gate goes live.
The effect: what the data shows and what it does not yet show
Data on the rhythm of work lets the plant set duty rosters. Since 82% of permits fall between 6:00 and 10:00, and 62 of 106 on Tuesday and Wednesday, security and approvers should be fully staffed exactly then. The plant also obtained a list of places where the location structure needs refining in the 3D map editor, so that a contractor selects a specific point at a machine and not a whole building.
To be fair, during the analysis period the QR gate, training and lone worker features did not yet exist as system data. The figures above describe the permit traffic that the QR scan is meant to handle, not the result of the gate itself. The first week of the period had 24 permits, probably shutdown work, which needs confirmation with the plant.
Hot work and work at height in the analysed period
Conclusions for plants with a similar profile
First, design the gate for the peak, not the average: traffic concentrates in a few hours, so that is when the scan and the verdict must work smoothly. Second, missing training should mean no entry at the gate, not a note in a report. Third, the evacuation list should be generated from actual entries and exits, not from a planned list. In a gatehouse audit this is the first point to check.
The solution supports meeting the employer cooperation requirement under Article 208 of the Polish Labour Code and provides evidence for audits, but the decision to admit a person remains with the plant.
Video
Frequently asked questions
Does the QR scan open the gate or barrier?
No. The system gives a verdict and records the scan, while the guard lets people in physically.
What happens to a person who did not scan out?
They move to the uncertain group on the evacuation list, flagged within a 24-hour window until the plant closes the matter.
Are the figures in this case the result of the QR gate?
No. They are permit traffic data from a period when there was no QR gate yet. They show the load the gate is meant to handle.