Process Safety Management (PSM): How to Implement It at Your Plant

A plant that handles hazardous substances is responsible for major accident scenarios, not only for workplace accidents. A process safety management (PSM) system organises this into a dozen or so linked elements, from process information to audit. Below you will find the implementation sequence, a realistic effort estimate and the evidence an auditor will ask for.

479
ZDR and ZZR plants in Poland (end of 2022)
Source: CIOP, Bezpieczeństwo Pracy 9/2024
6 weeks
time to launch a digital permit workflow at a chemical plant
89
person-days to implement PSM elements (illustrative calculation)
Source: illustrative calculation

Where the requirement comes from and who it applies to

The European basis is the Seveso III Directive (2012/18/EU) on the control of major-accident hazards. In Poland the requirements are implemented through the Environmental Protection Law provisions on preventing major accidents and the related implementing acts. Plants are divided into upper-tier (ZDR) and lower-tier (ZZR) establishments according to the quantity of hazardous substances; for anhydrous ammonia, for example, the threshold is 50 t for lower-tier and 200 t for upper-tier plants.

At the end of December 2022, Poland had 479 ZDR and ZZR plants in total (CIOP data). The Environmental Protection Inspectorate inspects upper-tier plants at least once a year and lower-tier plants at least once every 3 years. In practice, over a three-year cycle an upper-tier plant will face at least three inspections, a lower-tier plant one.

The term PSM comes from industrial practice and is not a concept in Polish statute. In the Polish context its equivalent is the safety management system required from Seveso plants. Even when a plant stays below the thresholds, the same elements work as good practice for installations with hazardous substances, and they often also follow from insurer or corporate group requirements.

PSM elements step by step

The set of elements is repeatable across most plants. Sequence matters, because each element builds on the results of the previous one: a hazard analysis based on outdated drawings produces false conclusions, and procedures written before the analysis have to be rewritten afterwards.

1. Process information

A complete set of P&ID drawings, mass and energy balances, substance data, protective device settings and safe operating limits. This set underpins every later analysis, so its currency is verified in the field, not only in the archive. A mismatch between a drawing and the installation is the first typical finding of a walk-down.

2. Process hazard analysis

Most often HAZOP according to PN-EN IEC 61882, supplemented with LOPA when protection layers need to be assessed. The result is a register of recommendations with an owner and a deadline. The analysis is repeated periodically and after every significant change.

3. Operating procedures and training

Procedures for start-up, normal operation, shutdown and emergency conditions, consistent with the results of the analysis. Operator training ends with a knowledge check, not with a signature on an attendance list.

4. Management of change (MOC) and pre-start-up review

Every change to the installation, material, setpoint or procedure goes through a risk assessment before implementation and a pre-start-up review after execution. This is the element where the whole structure most often breaks down, because changes during a turnaround are sometimes settled verbally.

5. Mechanical integrity, hazardous work, contractors

A plan of inspections for critical equipment and barriers, a permit system for hot work, confined space work and work at height, and requirements for external companies. In plants with a dozen or so contractors, this is where the largest number of organisational incidents arises.

6. Incident investigation, emergency plans, audit

Investigation of incidents and near misses, an emergency plan with drills, and a periodic audit of the whole system with a corrective action plan.

Effort to implement PSM elements (illustrative calculation)

Effort to implement PSM elements (illustrative calculation)Bar chart of implementation effort: HAZOP sessions 36, procedures 20, process information 15, MOC 10, audit 8 person-days010203040person-daysProcess informationProcess information: 15 person-days15HAZOP sessionsHAZOP sessions: 36 person-days36ProceduresProcedures: 20 person-days20MOC workflowMOC workflow: 10 person-days10Internal auditInternal audit: 8 person-days8
Source: Illustrative calculation: 12 nodes, 3 h per node, team of 6, 6 working hours per day

Sequence and effort: an illustrative calculation

The illustrative calculation below concerns an installation divided into 12 process nodes, a team of 6 people in the HAZOP session and 3 hours of team work per node. The assumptions are meant to show the order of magnitude, not an offer. HAZOP sessions amount to 36 hours of team work, that is 6 days of 6 hours. With 6 people this gives 36 person-days for the sessions alone.

On top of this come the preparation of process information (15 person-days assumed), updating procedures (20 person-days), launching the MOC workflow (10 person-days) and the first internal audit (8 person-days). In total 89 person-days, which for a team of 4 people means about 22 working days in calendar terms, not counting turnarounds and leave. A realistic schedule usually stretches to 4–6 months, because most of the time goes into closing out the recommendations.

  • Process information: 15 person-days
  • HAZOP sessions: 36 person-days
  • Operating procedures: 20 person-days
  • MOC workflow: 10 person-days
  • First internal audit: 8 person-days

The most common implementation pitfalls

The first pitfall is implementation on paper: a full set of procedures that nobody follows. The second is a hazard analysis done once and shelved, without revalidation after changes. The third is split ownership: maintenance runs MOC, the EHS department runs permits, and nobody sees both workflows at once.

The fourth pitfall concerns external companies. In a plant with about 20 maintenance contractors, several dozen people from outside the workforce pass through the site every month. If training, qualifications and the permit do not form a single path, it is impossible to show that the person performing hazardous work knew the risks and held valid qualifications.

Audit evidence: what should be at hand

A Seveso auditor asks for evidence, not declarations. The InnerWeb permit and training system provides audit evidence in the area of hazardous work: named invitations and training results, a register of companies and qualifications with expiry dates, permits with safeguard lists for hot work, work at height and confined space work, and QR checks in the field. Changes to selected data are recorded together with the author and time, which supports meeting the record-keeping requirement.

In an example deployment at a chemical plant, an NIS2 essential entity with about 20 external companies, the rollout took 6 weeks and up to 10 users worked on the plant side. The key point is that the MOC workflow is linked to the permit as a preparatory task, and the course of work is determined by a permit template configured on the data side of the installation.

The list of evidence to prepare before an audit: current drawings, the HAZOP recommendation register with statuses, the MOC register with pre-start-up reviews, the plan and results of barrier inspections, training records, the permit register and the results of emergency drills.

Video

Frequently asked questions

Is PSM mandatory in Poland?

The term PSM does not appear in Polish statute. However, upper-tier and lower-tier plants must implement a safety management system compliant with Seveso III. Other plants may apply PSM as good practice.

Where should implementation start?

With verifying process information in the field, because without current drawings the hazard analysis produces wrong conclusions. In parallel it is worth launching the MOC workflow, so that new modifications do not add to the documentation debt.

How long does implementation take?

The illustrative calculation points to about 89 person-days, and in calendar terms usually 4–6 months to the first internal audit. Closing out recommendations takes longer than producing them.

Does a permit system replace PSM?

No. It supports one of the elements, namely control of hazardous work and contractors, and provides audit evidence in that area. Hazard analysis and mechanical integrity remain the plant's responsibility.