InnerWeb
Skip to main content

Plant Turnaround Planning: A Practical Guide

A continuous-process plant issued 106 work permits in 9 weeks, a little over 2 per working day. A turnaround multiplies that load several times within a few weeks, so planning starts with the number of crews and permits, not with the work schedule.

106
permits in 9 weeks at a continuous-process plant
82%
of permits issued between 6:00 and 10:00
20
crews in the sample calculation
Source: example calculation

Where to start: scope and the shutdown window

A turnaround starts with a closed scope, not with the choice of contractors. The work list should come from three sources: inspections required by regulations and technical supervision, failures reported since the last shutdown, and modernization work that can only be done while the installation is stopped.

Every scope item needs an owner, a location on the installation and an approximate effort in man-hours. Without a location you cannot later calculate collisions, and without effort you cannot calculate crews. The scope is frozen a set number of weeks before the start, and later changes go through one person who decides on their impact on schedule and safety.

How many crews and permits: a sample calculation

The number of crews is determined by effort, window length and crew size. The sample calculation below shows a line of reasoning worth repeating on your own data. Assumptions: 24,000 man-hours of scope, a crew of 8 people, a 10-hour shift and a 15-working-day window.

Result: 24,000 divided by 8 people, 10 hours and 15 days gives 20 crews working in parallel. With one permit per crew per day, that is 300 permits in the window, or 20 per day. For comparison, a continuous-process plant in instance data issued 106 permits in 9 weeks, which with no permits at weekends gives about 2.4 per working day. The load therefore grows roughly 8 times, and with it the burden on approvers, security and the coordinator.

A margin for unplanned work and rework is added to the result. This figure is neither a product indicator nor a standard, only an example of the calculation: in every plant effort, crews and the number of days differ.

  • Effort from the scope: man-hours per item and location on the installation
  • Crew size and shift length agreed with contractors
  • Number of working days in the shutdown window
  • Number of permits per crew per day (one or more per crew)
  • Margin for unplanned work

Permits per working day: continuous operation and turnaround window

Permits per working day: continuous operation and turnaround windowBar chart: 2.4 permits per working day in continuous operation versus 20 in the sample turnaround window.05101520permits/dayContinuous operation (data): 2.4 permits/day2.4Continuous operation (data)Turnaround (calculation): 20 permits/day20Turnaround (calculation)
Source: (106 permits in 9 weeks, excluding weekends) and the sample calculation from the section on crews

When permits are created: lessons from 106 permits

Data from a continuous-process plant shows a pattern that sharpens during a turnaround. Of 106 permits, 82 percent were issued between 6:00 and 10:00, and 62 fell on Tuesday and Wednesday. The four largest companies accounted for 63 percent of permits, and two halls for 76 of the 106.

Planning conclusion: approvers and security need duty rosters for the morning peak, not spread evenly across the shift. During a turnaround this peak grows, so the queue of permits awaiting approval becomes a bottleneck before anyone starts work. Plan approver duty for the first hour of the shift and name deputies for every role.

Permit location matters

In the same data, 44 of 106 permits pointed to a building or "the whole line" instead of a specific machine. During a turnaround, when a dozen or so crews work in one hall, such a location makes collision detection impossible. The plant structure down to equipment level must therefore be completed before the start, not during it.

Contractor and permit list before the shutdown

The list of contractors should be closed several weeks before the start, divided into crews, qualifications and scope. That is when every person can be trained before arrival rather than at the gate, and the validity of their qualifications can be checked. The system supports this step: it checks the qualifications and training of assigned workers when a permit is created and warns about expiring entitlements.

Permits for particularly hazardous work are prepared in advance wherever possible. Work types (hot work, work at height, confined spaces) have their own protection lists, and for hot work the system enforces an observation period after completion. A permit request does not replace the on-site briefing, but it shortens it to confirming what has already been agreed.

Time of day permits are issued

Time of day permits are issuedDonut chart: 82 percent of permits were issued between 6:00 and 10:00, 18 percent in other hours.6:00–10:00: 82 % (82%)Other hours: 18 % (18%)100%6:00–10:0082 % (82%)Other hours18 % (18%)
Source: InnerWeb

Coordination with switching and isolation cards

On power and process installations, the order of isolations is a condition for admitting work. A work order is linked to a switching card, and preparatory tasks block the start until the last isolation is confirmed. Suspending work does not remove isolations, and a change in the configuration is a new task that conditions resumption.

When several jobs run on one system, the platform shows other active orders in the same location, and the work map presents their phase, hazards and protective measures. The order and roles follow the forms in force at the plant and are configured during workshops, not imposed in advance.

Preparation schedule and audit evidence

Turnaround preparation is worth laying out in stages counted back from the start: scope freeze, closing the contractor list, training before arrival, a trial of the permit process on a few jobs, and a general briefing. Each stage has an owner and a completion criterion, and the outcome is a record, not a verbal agreement.

After the shutdown, the record of permits, training and closures is material for the report: who worked where and when, which isolations were confirmed, what was suspended. It provides evidence for the internal audit and for the conversation with the insurer, and it does not replace the decisions of responsible people.

Example calculation

Number of crews and permits during a turnaround

Assumptions
ParameterValue
Work scope24,000 man-hours
Crew8 people
Shift10 hours
Shutdown window15 working days
Permits per crew1 per day

Result: 24,000 / (8 x 10 x 15) = 20 crews in parallel; 20 x 15 = 300 permits in the window, 20 per working day

Note: Sample calculation based on the assumptions above; in a real plant effort, crews and window length vary.

Checklist

Video

Frequently asked questions

How many weeks before the shutdown should the contractor list be closed?

Early enough to train every person before arrival and check their entitlements. The exact deadline depends on the number of companies and the plant, but closing the list at the start of the preparation window leaves time for additions.

Is 20 crews a standard figure?

No. It is a sample calculation showing the method. In every plant the result depends on effort, crews and the length of the shutdown window.

Why does permit location matter during a turnaround?

Because work collisions are detected by location on the installation. A permit that names only a building does not let you check whether two crews are working on the same equipment.

Does the system replace the pre-work briefing?

No. It supports the briefing, because agreements on isolations, hazards and the place of work are recorded in the permit and visible to all participants.

Sources

Plan your turnaround with data from your own permits

Let us talk about how to calculate crews, the permit queue and duty rosters before your turnaround.

Let's talk