Starting point
The plant runs refining and petrochemicals within an international group and, as an NIS2 essential entity, is responsible for the whole supply chain, including the physical one. About 20 external firms work in maintenance. Every major job brings crews in which the foreman knows the rules, but not every crew member has completed induction training.
Permit requests circulated on paper, so the dispatcher had no current picture of open jobs. The validity of qualifications such as SEP, UDT or work at height was checked by hand. The order of safeguards, measurements and signatures depended on the discipline of individuals, not on enforcement in the process.
- induction training at the gate that delays the start of work
- no certainty that every person in the crew was trained
- manual tracking of qualification expiry dates
- paper permits without a picture of open jobs
Why this is a supply chain problem
The Polish National Cybersecurity System Act (KSC), which implements Article 21 of NIS2, requires supply chain security within the information security management system. In a chemical plant a supplier is also a person entering a confined space, along with their phone, service laptop or access card. Without control of this path there are gaps in both OHS and cybersecurity.
What matters to an auditor is whether the plant can show who received access and on what basis. The obligations of chapter 3 of the Act apply by 3 April 2027, and the first audit of an essential entity by 3 April 2028. The plant decided it needed a trail of external access before an auditor asks for it.
Deployment cost structure (share by item)
Solution: one path from training to permit to check
The plant introduced a path in which an external person is trained before arrival and the permit is created in the system. InnerWeb delivered the solution as software on a separate server, with no need to build infrastructure on the plant side.
Training before arrival
Each person receives a personal invitation with a QR code by e-mail or SMS. Online training ends with a test of randomly drawn questions and a declaration, available in two languages. The system does not allow a permit for a person without current training, and expiry dates and reminders for periodic training are handled by the register of firms and qualifications.
Digital permit
A permit is created in a dozen or so seconds, goes through approvals and is printed as a PDF in one of the plant's two templates. Hot work, work at height, work in confined spaces and work on energy equipment each have their own safeguard lists. Authorization matrices control who may issue and approve a permit.
Field check
Scanning a person's QR code shows their training, qualifications and the permit for today. The inspector does not need to call the dispatcher or leaf through a binder.
Result: numbers from the deployment
Launch took about 6 weeks. On the plant side up to 10 people use the system, while employees of external firms are not counted as users and generate no licence costs, regardless of how many are trained. The plant invested nothing in infrastructure.
The scope covered five items: a server with accounts for 50 people and administrator training, a training module in two languages, permits with particularly hazardous work, QR checks in the field, and workplaces with a register of about 20 firms. The deployment falls in a range of PLN 12–13 thousand net, payable in two instalments: on order and after acceptance of the launch. Monthly maintenance for 10 users is around PLN 2 thousand net (indicative ranges from 2025–2026 deployments; individual quotation).
The cost structure shows that almost 60% of the value is the training module and permits, the two functions that directly build the evidence of contractor access.
What the plant gained as audit evidence
The full path of training, qualifications, permit and check is recorded with date and person. It serves as evidence for inspections by the National Labour Inspectorate (PIP), corporate audits and the insurer, and supports meeting the supply chain security requirement in a cybersecurity audit. The system provides evidence; it does not replace the plant's decision on the scope of admissions.
The offer was deliberately limited to training and permits, without locating people. Location can be added later on the same instance if needed, for example for a list of people on site during an evacuation.
Lessons for other plants
First, train every person from an external firm before arrival so that training is not a bottleneck at the start of the working day. Second, enforce the order of steps for particularly hazardous work in the system instead of relying on memory. Third, plan accounts for more people than the first scenario requires, to avoid a second deployment. Fourth, record the whole path as evidence, because that is what will be asked about in an audit.
Video
Frequently asked questions
Do employees of external firms pay for licences?
Not in the described variant. Counted are users on the plant side and firm coordinators who announce their people. Employees of external firms and guests generate no licence cost.
Does the system enforce the order of steps for hot work?
Yes. Types of particularly hazardous work have their own safeguard lists, and authorization matrices link the type of work to the required qualifications.
Does the solution locate people on site?
Not in this scope. Location can be added later on the same instance, but the offer in this case did not include it.