CRA When Buying a PLC Controller for a Chemical Plant

A chemical plant, an NIS2 essential entity, plans to buy 60 PLC controllers to modernise a process installation. The supplier operates in the EU market, so its product falls under the Cyber Resilience Act. The procurement and OT teams must decide what evidence to collect from the supplier before signing the contract and what it costs.

PLN 7,480
cost of extra supplier verification (assumptions in the text)
Source: example calculation
about PLN 125
verification cost per controller
Source: example calculation

Starting situation

This is a generic case based on typical assumptions: a chemical plant with about 2,000 employees, several process installations and an OT network divided into zones. The modernisation replaces 60 PLC controllers with an Ethernet interface in new control cabinets. The plant is an NIS2 essential entity, so under Article 21 of Directive 2022/2555 it must account for supply chain security and the acquisition of systems.

The previous procurement specification contained functional requirements and machinery safety standards. Product cybersecurity was covered by one general paragraph, with no specific evidence for the supplier to provide.

The problem: what the CRA changes in this purchase

A controller with a network interface is a product with digital elements. From 11 September 2026 its manufacturer must report actively exploited vulnerabilities with an early warning within 24 hours, a notification within 72 hours and a final report, and the regulation applies in full from 11 December 2027. For the plant this raises two questions: does the supplier have a process in place, and will the device receive updates throughout the service life of the installation, which in the chemical industry can exceed 10 years.

The regulation requires a support period of at least 5 years, unless the expected product lifetime is shorter. This minimum does not cover the full life cycle of a process installation, so the plant should negotiate a longer contractual commitment.

Components of the extra supplier verification cost

Components of the extra supplier verification costHorizontal chart: PLN 3,360 document review, PLN 2,800 legal clauses, PLN 1,320 procurement coordination.01000200030004000PLNOT document reviewOT document review: 3360 PLN3360Legal clause reviewLegal clause review: 2800 PLN2800Procurement coordinationProcurement coordination: 1320 PLN1320
Source: Worked example based on the assumptions in the cost section

The solution: an evidence package from the supplier

The procurement team added to the request for quotation a list of documents the supplier must provide before the order. The list supports meeting the requirement in a supply audit and follows the logic of IEC 62443-4-1 (secure development life cycle) and 62443-4-2 (component requirements).

  • The manufacturer's declaration on CRA compliance status and the conformity assessment plan for the controller series.
  • An SBOM in an agreed format for the firmware version that will reach the plant.
  • A declared support period with the end date of security updates.
  • A description of the vulnerability reporting and coordinated disclosure process, and a contact for the security team.
  • Default configuration: no factory passwords, unnecessary services disabled, support for signed updates.
  • A contract clause on notifying the plant about vulnerabilities affecting the delivered devices.

Worked example: the cost of extra verification

The team estimated the cost of extra supplier verification for one order. This is a worked example on explicit assumptions, not an offer or a quote for a specific deployment. The review of documents (SBOM, declarations, vulnerability policy) was assumed at 24 hours of OT engineer work at PLN 140/h, or PLN 3,360. A lawyer's review of contract clauses is 8 hours at PLN 350/h, or PLN 2,800. Talks with the supplier and agreeing requirements by procurement take 12 hours at PLN 110/h, or PLN 1,320.

The total is PLN 7,480, or about PLN 125 for each of the 60 controllers. For comparison, replacing a controller withdrawn by the manufacturer before the end of planned service, assuming PLN 4,000 per unit including works, would cost PLN 240,000 for the whole batch.

How to read this comparison

Verification does not eliminate the risk of a product withdrawal, but it lowers its probability and gives a contractual basis for claims. The result depends on the number of units and the rates at a given plant, so treat it as a calculation template.

Supplier verification versus replacing a withdrawn batch

Supplier verification versus replacing a withdrawn batchComparison: PLN 7,480 of verification against PLN 240,000 to replace the batch.050,000100,000150,000200,000250,000PLNVerification before purchase: 7480 PLN7480 PLNVerification before purchaseReplacing 60 controllers: 240,000 PLN240,000 PLNReplacing 60 controllers
Source: Worked example: 60 units at PLN 4,000 including works

Effect and conclusions

After introducing the evidence package, the plant received comparable data in the offers on the support period and the vulnerability process, which it had not had before. Bidders who declared a support period longer than the regulation's minimum scored better, and missing SBOMs had to be supplied by a set deadline. The plant added these commitments to its supplier risk register and linked them to update control during operation.

The general conclusion: the cost of verification is small compared with the order value and the cost of a forced replacement. It is worth writing CRA requirements into the request template so that later purchases do not repeat the work.

Example calculation

Extra verification of a PLC supplier (60 controllers)

Assumptions
ParameterValue
OT document review24 h × 140 PLN
Clause review by a lawyer8 h × 350 PLN
Procurement coordination12 h × 110 PLN
Replacement cost per withdrawn unit4 000 PLN/unit

Result: Verification PLN 7,480 (about PLN 125 per unit) against PLN 240,000 for a possible batch replacement.

Note: Worked example; rates and hours depend on the plant.

Video

Frequently asked questions

Must the plant assess the controller's CRA compliance itself?

No. The manufacturer performs the conformity assessment and CE marking. The plant collects evidence that the supplier has a process, an SBOM and a support period, and records it in the procurement file.

What if the supplier does not have an SBOM yet?

It is worth writing a delivery deadline and the consequences of delay into the contract. The regulation requires vulnerability handling throughout the support period, so a missing component list is a risk signal.

Is IEC 62443 mandatory in procurement?

The standard is voluntary, but it is a recognised framework of requirements for the supplier and integrator. Citing it in the specification supports meeting the due diligence requirement in the supply chain.