Contractor risk assessment at a chemical plant

A chemical plant, an essential entity under NIS2, works with about 20 external contractors on maintenance and admits dozens of non-employees to work every month. This case shows how contractor risk assessment stopped being paper in a binder and became a path: training before arrival, a permit with risks, a check in the field.

6 wks
time to launch
about 20
external companies in maintenance

Starting point

The plant runs refining and petrochemical operations as part of an international group. Maintenance relies on about 20 external companies performing hot work, work at height and work inside tanks. On the plant side, up to 10 users are to work in the system, while contractors are dispersed and change from week to week.

Work permits lived in binders. There was no current picture of open jobs, and the validity of qualifications (electrical, pressure equipment, work at height) was tracked by hand. On paper, nothing enforced the order of safeguards, measurements and signatures.

The problem: risk assessment ended at the gate

Article 226 of the Polish Labour Code requires that an employee knows the risks connected with their work, and Article 208 adds a duty of cooperation between employers operating in the same place. At the plant, risk assessment existed for its own workstations, but for external crews it came down to an induction at the entrance.

The initial training took place at the gate and delayed the start of work. It was also hard to confirm that every person in the crew had completed it, not only the foreman. Information about risks in a specific location, for example next to a live installation, reached the contractor too late or not at all.

Monthly entry training time at the gate

Monthly entry training time at the gateBefore and after chart: 50 hours of training at the gate per month drops to zero after training moves before arrival01020304050hrsTraining at entry (Hours at the gate): 50 hrs50 hrsTraining before arrival (Hours at the gate): 0 hrs0 hrsHours at the gateTraining at entry (Delay to work start): 50 hrs50 hrsTraining before arrival (Delay to work start): 0 hrs0 hrsDelay to work start
  • Training at entry
  • Training before arrival
Source: Sample calculation: 100 people per month, 30 min of training per person

The solution: one path from training to inspection

The plant introduced a path in which every link feeds the next. First a personal invitation with a QR code sent by e-mail or text message. Then online training with a test of randomised questions and a declaration in two language versions. Next, a register of companies and qualifications with expiry dates and reminders: the system does not admit a person without current training.

A digital permit is created in a dozen or so seconds, goes through approvals and prints as a PDF in one of two plant templates. Types of particularly hazardous work have their own safeguard lists, and authorisation matrices control who can issue and approve a permit.

Risks are part of the permit. The risk catalogue is assigned to locations at every level of the plant hierarchy and to the type of hazardous work, through the catalogue of risks and protective measures, so the contractor sees the risks and required protective measures before starting. On the printout they appear in five sections without repetition.

Inspection in the field

Scanning a person's QR code shows their training, qualifications and today's permit in the field. The inspector does not look for paper but checks the status. The offer deliberately excluded personnel location: no beacons, wristbands or position tracking. The plant can add it later on the same instance.

The effect in numbers

The deployment was closed at a single price: a server with accounts for 50 people, a training module in two languages, permits with particularly hazardous work, QR inspection, workplaces and a register of companies. Time to launch was 6 weeks, and no additional infrastructure was needed on the client side. Employees of external companies are not counted as licence users, regardless of how many are trained.

The sample calculation below shows the time saved at the gate. Assumptions: 20 companies, on average 5 people entering per month from each, so 100 people; entry training of 30 minutes per person.

  • At the gate: 100 people × 30 min = 50 hours per month of delayed work starts
  • Before arrival: remote training, and at the gate only a QR check lasting a few seconds remains
  • Periodic training: the plant sets the validity period (for example 12 months), after which the person receives an invitation to retrain

Conclusions for plants with contractors

First, contractor risk assessment starts before they arrive. Second, risks should be assigned to a place and a type of work, not described in general terms in an instruction. Third, the order of steps in hot work and confined spaces is worth enforcing in the system instead of relying on discipline.

The full path of training, qualifications, permit and inspection is evidence for the labour inspectorate (PIP), a corporate audit and the insurer. The system provides audit evidence but does not release the employer from its duties. Quotes for deployments of this type usually fall in a range of roughly PLN 10,000–20,000 net (indicative range from 2025–2026 deployments; individual quote).

Video

Frequently asked questions

Do employees of external companies count as licence users?

Not in the case described. The licence covers people working in the system on the plant side and company coordinators who announce workers and submit requests.

Does the system track the validity of training and qualifications?

The register of companies and qualifications has expiry dates and reminders, and the system does not admit a person without current training. The plant sets the validity period.

Does the solution include locating people on the plant site?

Not in this case. The scope deliberately left out beacons and position tracking, and location can be added later on the same instance.