What a plant should treat as a confined space
In industrial practice, a confined space is a place with limited entry and exit that is not designed for continuous occupancy and whose atmosphere may be hazardous: too little oxygen, flammable gases, vapours or toxic substances. Tanks, reactors, process ducts, manholes, chambers, silos and ventilation ducts are typical examples. The definition and the list of locations are set by the plant on the basis of Polish occupational health and safety (OHS) rules and its own risk assessment, so the first document is the plant register of confined spaces, not the permit form.
For each location the register should state: where it is, what medium it holds or held, how it is entered, what ventilation is required and who is authorised to issue entry approval. Without such a register, the issuing person assesses the space from scratch every time, and contractors receive information verbally. The register is also where the risk assessment returns after every change to the installation.
The procedure step by step
This sequence works in plants where confined space work is done both by the in-house maintenance team and by external contractors. Polish OHS rules for particularly hazardous work require, among other things, designated responsible persons, written instructions, protective equipment and safeguarding. The list below arranges these requirements into a chain of actions that can be reproduced and documented.
- Define the task, the location and the time window: what is done, in which tank or duct, and for how long.
- Assess the risk: atmosphere, product residues, energy (power supply, agitators, valves), temperature, limited visibility, escape options.
- Prepare the installation: empty it, cut off inflows, isolate energy, ventilate, mark the space.
- Appoint the people: the person in charge, the attendant at the entry point, the entrants and the rescue team.
- Test the atmosphere before entry, and during the work test at set intervals or continuously.
- Check the qualifications and medical fitness of the people, the protective equipment and the rescue equipment.
- Issue the permit after approval by a person on the plant side and hold a briefing before entry.
- Keep a record of the people inside and maintain communication with the entrants.
- Close the work: count the people, remove the safeguards, restore the installation and close the permit.
Permit issue and closure time (illustrative calculation)
- Paper
- Electronic system
Risk assessment and atmosphere testing
Risk assessment does not end with the statement that the tank is empty. An emptied tank may hold sludge that releases vapours when disturbed, and steel and coatings can absorb oxygen. The assessment therefore covers the history of the medium, the cleaning method and the expected reaction products. The result translates into a list of protective measures: mechanical ventilation, breathing apparatus, clothing, and lighting rated for use in a hazardous explosive area.
Atmosphere testing is performed by a trained person, with an instrument that has a current calibration, and the result is recorded in the permit together with the time. A single test before entry is not enough if the work lasts longer or generates vapours, for example solvent cleaning or hot work. In that case the plant sets the testing frequency or requires a continuous detector worn by the entrant.
The role of the attendant and rescue
The attendant stays at the entry point for the whole duration of the work and performs no other tasks. The duties are to keep a record of the people inside, maintain communication, watch for warning signs and start the rescue without entering. The most common mistake is reassigning the attendant to other work when "everything is going smoothly". In many confined space accidents, the further victims are people who entered to help without protection.
The rescue plan is prepared before the permit is issued: who rescues, with what equipment, from which assembly point and within what time. The plant checks that the retrieval equipment (tripod, winch, lines) fits the geometry of the entry. A drill on this tank or on a model of it reveals limitations that a document will not show.
How an electronic permit supports the procedure
In InnerWeb, a work permit is an electronic document that passes through the preparation, main work and closure phases, and the system checks the dates and the qualifications of the assigned workers when the permit is created and opened. A particularly hazardous job, for example in a confined space or at height, is a separate object attached to the permit, with its own workflow. Approving or rejecting such a job is reserved for a user on the plant side, not for the contractor.
The system enforces the order of the steps, not the memory of the participants. A hazardous job cannot be closed while more than one person remains on site, which protects against closing a permit with a person still inside. The plant has a live view of who is doing which work and where. The system does not replace the works manager or the issuing person: it supports meeting the requirement and provides evidence for the audit.
Permit closure and audit evidence
Closure starts with counting the people and checking that the space is empty and the tools are out. Only then are the safeguards removed and the installation restored. The evidence the plant will show to an inspector, an insurer or a corporate auditor includes: the register of spaces, the risk assessment, the test records, the list of people with qualifications, entry and exit times, approval on the plant side and confirmation of closure.
The example calculation in the chart shows how long each step takes under these assumptions: the issuing person prepares a paper permit in 40 minutes and an electronic one in 12 minutes; closure takes 20 and 8 minutes respectively. The difference comes mainly from the absence of re-typing data and from ready-made risk templates. This is an illustrative calculation, not a measurement from a specific plant.
The most common pitfalls
The first pitfall is a register of spaces that exists but is not updated after a refurbishment. The second is contractor qualifications checked only for the foreman, not for every person entering. The third is a permit issued for a whole week without re-testing after a break. The fourth is communication that works on the surface but not deep inside the tank. Each of them can be closed with a simple rule: a separate entry in the permit, a repeat test after a break longer than the agreed limit, and a communication check before entry.
Checklist
Video
Frequently asked questions
Is every tank a confined space?
Not every one. What decides is limited entry and exit, no design for continuous occupancy and the possibility of a hazardous atmosphere. The plant confirms this in the register and the risk assessment.
Who should test the atmosphere?
A trained person, using an instrument with a current calibration. The result goes into the permit together with the time and the details of the person testing.
Can the attendant help an entrant in an emergency?
The attendant does not enter. The task is to call the rescue and maintain communication, while retrieval is done with equipment from outside or by a trained team.
What does an electronic system add to a paper procedure?
It enforces the order of steps, checks dates and qualifications and keeps a record for the audit. It does not replace the works manager or the issuing person.
Sources
See a tank entry permit in practice
We will show, on your register of spaces, what the permit, the test and the closure with audit evidence look like. Book a conversation or a demo.
Let's talk