Access control schedule and work permits: implementation notes

The maintenance manager must align the access control time window with the dangerous work permit and with an InnerWeb visit when a service technician enters outside the standard shift. Below are the stages, pitfalls and order of settings for a production plant, with a clear boundary between what the access control system does and what InnerWeb does.

377 days
maximum lead time for planning a visit
Source: unit card
34 days
maximum number of days planned at once
Source: unit card

Problem: three clocks that must agree

A technician's entry on a Saturday night depends on three independent things: the time window of the permission in the access control system, the permit for dangerous work and, for people with no work to do, a visit planned in InnerWeb. If any of these elements has a different time range, the technician stands at the gate and the outage on the line goes on.

The point is not for one of these things to replace the others. The access control system is responsible for the time and place of entry, the permit for admission to work, and InnerWeb for the verdict on the person's readiness and the entry record. Alignment means making sure the time ranges overlap.

Stage 1: separate the visit from the permit

A planned visit is the equivalent of a one-day permit for a person arriving without work to perform, and removes only the permit requirement. A technician performing dangerous work needs a work permit, not a visit. A visit makes sense for a supplier arriving for a meeting or pickup, not for a repair.

Each planned visit has a host who is an active internal employee, and an external company coordinator does not plan visits. For the maintenance manager this usually means the host is someone from their team.

Example work range and window in the access control system

Example work range and window in the access control systemComparison chart: a permit for 6 hours of work and an access control window of 7 hours with the margin02468hoursWork permit: 6 hours6 hoursWork permitAccess control window with margin: 7 hours7 hoursAccess control window with margin
Source: Example calculation: 6 hours of work plus a one-hour margin for approach and departure

Stage 2: access control window consistent with the permit

The window of the permission in the access control system should cover the whole range of work with a margin for approach and departure, but not longer than needed. A window that is too short blocks the technician's return for tools, and one that is too long leaves access open after the work is finished.

A visit in InnerWeb can be planned for any days from today, up to 377 days ahead and up to 34 days at once. For a repair spread over several days this is convenient, but the windows in the access control system and the visit dates should come from one work schedule kept by the maintenance manager.

Stage 3: entry outside the standard shift

When a technician enters outside the shift, the access control schedule will naturally reject them. The exception from the schedule is approved by the supervisor and carried out by security, with an entry in the register. We describe the practice in the material on exceptions in the schedule.

The entry verdict in the security panel has four components: no missing trainings, no missing qualifications for dangerous work, a permit or visit for today, and an active account. An approved exception in the access control system does not remove any of them, so a technician without qualifications for dangerous work does not enter even if the gate lets them through.

Stage 4: evidence and closing the day

After the work is finished the exit should be recorded. For an external company the default stay limit is 12 hours, and automatic checkout records the exit. For an internal employee the day is marked as no exit and the employee confirms the hour.

The card webhook of the access control system passes to InnerWeb the swipe with the reader place, but it does not store direction or event identifier, so it does not replace the scans in the security panel. Events from a place without a template in InnerWeb go to the log. The technician's entry record is therefore better based on the scan in the panel, with the access control swipe treated as a supplement.

Pitfalls and order of settings

The list below orders the settings so that entry outside the shift does not depend on chance.

  • First the work plan with time ranges, then the windows in the access control system
  • Work permit for dangerous work, visit for guests with no work
  • A host for the visit from the maintenance team
  • Checking that the technician's qualifications are current before the work day
  • Rule for entry outside the shift written into the procedure
  • Night entry test before the first repair

Video

Frequently asked questions

Does a visit replace the permit for dangerous work?

No. A visit replaces the permit only for a person arriving without work to perform. Dangerous work requires a permit.

Does an exception in the access control system release from qualifications?

No. The InnerWeb verdict still checks trainings, qualifications and an active account, so a lack of qualifications ends in a refusal.

Can a visit be planned for a longer repair?

Yes, up to 34 days at once and up to 377 days ahead, but the access control windows and dates should come from one work schedule.